Chinese New Year and Your Supply Chain: How to Plan Around It
Chinese New Year (春节, Spring Festival) is the longest and most disruptive holiday in the Chinese manufacturing calendar. Factories close for 2–4 weeks, workers return to their home provinces, and production capacity drops significantly before and after the holiday as workers travel and factories deal with labour turnover. Importers who do not plan for it routinely miss their stock replenishment windows and face empty shelves in Q1 and Q2.
Key facts at a glance
• Chinese New Year falls on a different date each year (late January to mid-February). It is determined by the lunar calendar. 2025: January 29. 2026: February 17. 2027: February 6
• Most factories close for 7–15 days of official holiday, but the effective disruption period is 4–6 weeks: a “pre-CNY rush” slows lead times from early January, and many factories do not return to full capacity until mid-March due to worker turnover
• Worker attrition is a real risk: 10–30% of a factory’s production workers may not return after CNY, particularly after payroll processing. This affects quality and lead time predictability in February–March
• Freight rates spike significantly in the weeks before CNY as manufacturers rush to ship, and again in mid-March as factories resume; booking early provides some protection
The Chinese New Year supply chain calendar
Chinese New Year dates (next 3 years)
| Year | CNY date | Zodiac | Factory closure (typical) | Full recovery (typical) |
|---|---|---|---|---|
| 2025 | 29 January | Snake | 24 Jan – 7 Feb | Mid to late March |
| 2026 | 17 February | Horse | 12 – 26 Feb | Late March to early April |
| 2027 | 6 February | Goat | 1 – 15 Feb | Mid to late March |
Use the pre-CNY window to build a buffer stock position
If you have predictable demand in Q1–Q2, build a 6–8 week buffer stock position with a production run that completes and ships in early January — before the pre-CNY rush degrades quality and before freight rates peak. This buffer covers the factory closure period and the recovery period. The cost of holding extra inventory for 2 months is usually lower than the cost of a stockout, air freight to cover a delayed sea shipment, or accepting goods that passed inspection but were produced under end-of-year rush conditions.
Quality risk is highest in the 2–3 weeks before CNY closure
The period immediately before the holiday closure is one of the highest quality-risk windows in the production calendar. Factories are under pressure to clear backlogs, production workers are distracted by travel planning and bonus expectations, and management attention is on logistics rather than quality. If your goods are completing production in this window, do not waive the pre-shipment inspection — it is precisely when inspections are most valuable. Some importers schedule their PSI for this period as standard practice, knowing that the inspector may catch issues that would not appear at other times of year.
Frequently asked questions
MandarinDesk helps importers plan their China sourcing calendar around factory holidays and manage the pre-CNY rush with proactive inspection and freight booking. Contact us.
Related reading
Need a hand?
Tell us what you need done in China. We reply within 24 hours with a fixed price and timeline.