Chinese New Year and Your Supply Chain: How to Plan Around It

Chinese New Year and Your Supply Chain: How to Plan Around It
MandarinDesk · China SourcingUpdated November 20264 min read

Chinese New Year (春节, Spring Festival) is the longest and most disruptive holiday in the Chinese manufacturing calendar. Factories close for 2–4 weeks, workers return to their home provinces, and production capacity drops significantly before and after the holiday as workers travel and factories deal with labour turnover. Importers who do not plan for it routinely miss their stock replenishment windows and face empty shelves in Q1 and Q2.

Key facts at a glance

• Chinese New Year falls on a different date each year (late January to mid-February). It is determined by the lunar calendar. 2025: January 29. 2026: February 17. 2027: February 6

• Most factories close for 7–15 days of official holiday, but the effective disruption period is 4–6 weeks: a “pre-CNY rush” slows lead times from early January, and many factories do not return to full capacity until mid-March due to worker turnover

• Worker attrition is a real risk: 10–30% of a factory’s production workers may not return after CNY, particularly after payroll processing. This affects quality and lead time predictability in February–March

• Freight rates spike significantly in the weeks before CNY as manufacturers rush to ship, and again in mid-March as factories resume; booking early provides some protection

The Chinese New Year supply chain calendar

Nov – early Dec
Place pre-CNY orders
Place any orders that need to ship before CNY. Factories running at full capacity have the best quality control now. Confirm cargo-ready dates with your suppliers.
Mid-Dec – early Jan
Pre-CNY rush begins
Factories accelerate output to clear order backlogs before closing. Lead times extend, quality inspection becomes more critical as factories cut corners to hit volume targets. Conduct pre-shipment inspections on any goods completing in this window.
~2 weeks before CNY
Freight booking deadline
Book ocean freight and air freight for pre-CNY shipments now. Carriers fill quickly and rates increase. Many factories ship goods to the port without confirmed booking space in this period.
Factory closure
Holiday period (7–15 days)
Factory offices and production lines close. Email responses stop or are severely delayed. Do not expect any communication or production activity during this period.
Post-CNY: weeks 1–2
Partial reopening
Factories officially reopen, but are often running at 50–70% capacity as workers return gradually from their home provinces. Quality issues are more common as new workers are onboarded and production lines restart.
Post-CNY: weeks 3–6
Recovery period
Most factories approach normal capacity by mid-March. Worker turnover situation becomes clearer — factories with high attrition take longer to stabilise. Best time to visit the factory and confirm capacity for Q2 orders.

Chinese New Year dates (next 3 years)

YearCNY dateZodiacFactory closure (typical)Full recovery (typical)
202529 JanuarySnake24 Jan – 7 FebMid to late March
202617 FebruaryHorse12 – 26 FebLate March to early April
20276 FebruaryGoat1 – 15 FebMid to late March

Use the pre-CNY window to build a buffer stock position

If you have predictable demand in Q1–Q2, build a 6–8 week buffer stock position with a production run that completes and ships in early January — before the pre-CNY rush degrades quality and before freight rates peak. This buffer covers the factory closure period and the recovery period. The cost of holding extra inventory for 2 months is usually lower than the cost of a stockout, air freight to cover a delayed sea shipment, or accepting goods that passed inspection but were produced under end-of-year rush conditions.

Quality risk is highest in the 2–3 weeks before CNY closure

The period immediately before the holiday closure is one of the highest quality-risk windows in the production calendar. Factories are under pressure to clear backlogs, production workers are distracted by travel planning and bonus expectations, and management attention is on logistics rather than quality. If your goods are completing production in this window, do not waive the pre-shipment inspection — it is precisely when inspections are most valuable. Some importers schedule their PSI for this period as standard practice, knowing that the inspector may catch issues that would not appear at other times of year.

Frequently asked questions

What other Chinese holidays affect production?
Besides Chinese New Year, the main holidays that affect factory production are: National Day Golden Week (国庆黄金周, 1–7 October, with many factories taking 7–10 days), Labour Day (劳动节, 1–5 May, usually 5 days), and Qingming Festival (清明节, early April, usually 3 days). National Day Golden Week is the second most disruptive holiday after CNY — factories in export-heavy regions often close the full week, and freight volumes spike the week before. Mid-Autumn Festival (中秋节, 15th day of the 8th lunar month, usually September) is typically 1–3 days and has less supply chain impact. For a complete calendar, ask your supplier directly for their planned closure dates at the start of each year.
Can I still place orders during CNY?
Yes — you can send enquiries and purchase orders during the holiday period, but do not expect responses until the factory reopens. It is worth noting that placing orders immediately after the holiday reopening is very common, and factories often have a backlog of new orders waiting when they return. If your production is not time-sensitive, waiting 2–3 weeks after the holiday to place orders (once the factory has stabilised its workforce) may result in better lead time reliability than placing immediately on reopening day. For time-sensitive orders, place them before the holiday and confirm production start dates as soon as the factory reopens.

MandarinDesk helps importers plan their China sourcing calendar around factory holidays and manage the pre-CNY rush with proactive inspection and freight booking. Contact us.